Inspection Regime
Recertification and milestone inspections in Miami-Dade
Two separate requirements overlap here, one from the county and one from the state, and confusion between them is routine. This sets out who each covers, at what age, on what cycle, and what the structural repair work that follows a report looks like.
If you own or serve on the board of an older building in Miami-Dade, at some point a letter arrives requiring an inspection, and shortly afterward an engineer's report arrives listing things that need repairing. Two different rules can produce that letter. They are not the same rule, and a building here can be subject to both.
Miami-Dade building recertification
This is a county program, and it is decades old. It requires covered buildings to be inspected by a licensed engineer or architect and certified as structurally and electrically safe, then re-inspected on a repeating cycle.
Under the current rules:
- Condominium and cooperative buildings of three stories or more, within three miles of the coast, built in 1998 or later: first recertification at 25 years, then every 10 years.
- All other covered buildings built in 1993 or later: first recertification at 30 years, then every 10 years.
- Transitional cases: coastal buildings constructed between 1983 and 1997, and all others constructed between 1983 and 1992, were required to recertify by 31 December 2024. Buildings from 1982 and earlier continue on the schedule already established for them.
- Exempt: single-family homes, duplexes, and buildings with an occupant load of ten or fewer and 2,000 square feet or less.
The report is due within 90 days of the Notice of Required Inspection. The county's published fee schedule sets the application fee at $375.00, with a higher figure for late submission and a per-trade fee for re-review of a subsequent report. The program applies countywide, but each of the county's municipalities administers it through its own building official, so the practical contact is your city rather than the county unless the property is unincorporated.
The Florida milestone inspection
This is a state requirement under Florida Statutes section 553.899, created in the wake of the 2021 Surfside collapse and amended since. It is narrower than the county program in what it covers and broader in where it applies.
- Who: buildings of three habitable stories or more that are under condominium ownership (chapter 718) or cooperative ownership (chapter 719).
- When: the initial milestone inspection at 30 years from the certificate of occupancy, then every 10 years after that.
- The coastal question: the 2022 legislation created an automatic 25-year trigger for buildings within three miles of the coastline. That automatic trigger was repealed in 2023. What remains is discretionary: a local enforcement agency may determine that local circumstances, including environmental conditions such as proximity to salt water, require the inspection at 25 years. It is no longer automatic, and this is the single most commonly out-of-date fact circulating on the subject.
- Deadlines: the phase one inspection is due within 180 days of notice, with a phase two progress report within 180 days of the phase one report where phase two is triggered.
- Exempt: single-family, two-family, three-family, and four-family dwellings with three or fewer habitable stories above ground.
Alongside this sits the structural integrity reserve study requirement for associations, which is the mechanism intended to ensure the money for structural work exists when the report calls for it.
What the reports typically find
On a Miami-Dade building of the relevant age, the dominant finding is concrete restoration. Balcony slabs and edges, walkway soffits, tie beams, lintels, columns at ground level, and slab edges at the perimeter. The mechanism behind almost all of it is chloride-induced corrosion of embedded reinforcement, covered in detail in the spalling guide.
Beyond concrete, reports commonly list corroded structural steel, failed balcony railing connections, deteriorated waterproofing over structural elements, and stucco delamination. Foundation and settlement items appear less often, because in this county settlement is not the usual failure mode for a mid-rise building on the ridge.
What happens between the report and the finished work
- The repair schedule. The engineer's report normally includes a schedule with quantities and locations. That document, not a contractor's opinion, is the basis for everything that follows.
- Quantity takeoff and pricing. Priced against the schedule, so the board can see how the number was built rather than receiving a lump sum.
- Permit submittal. Based on the engineer's drawings. Miami-Dade requires plans submitted through its portal to be digitally signed and sealed.
- Demolition and sounding. The point at which quantities change. Sounding finds delaminated concrete that visual inspection could not, so expect the number to move. A sensible contract sets a unit rate for additional square footage in advance.
- Phased execution. On an occupied building, staging, protection, and maintaining access are a real cost line rather than an afterthought.
- Close-out. Documentation the engineer can sign against, so the file closes rather than lingering.
Two practical points for boards
First, budget for growth from the outset. Restoration quantities almost always increase after demolition begins, and a project priced with no contingency is a project heading for a second assessment.
Second, sequence the waterproofing with the concrete. Repairing a balcony slab beautifully and then reinstating a failed membrane over it starts the same clock again. The scope should treat the water path and the concrete as one job. Repair scope detail is on the recertification repairs page.
Get a free quote
Call (786) 841-1091 or send the quote form. Describing what you are seeing costs nothing, and so does the written quote that follows.
Questions on this
Does my house need any of this?
Who pays for the repairs in a condominium?
What happens if the deadline passes?
We are buying into a building. What should we look at?
Sources
- Miami-Dade County building recertification, for intervals, exemptions, and deadlines.
- Miami-Dade Implementing Order 4-63, effective 30 June 2025, for recertification and permit fees.
- Florida Statutes 553.899, milestone inspections.
- Senate Bill 154 (2023), which repealed the automatic 25-year coastal trigger.
These rules have been amended more than once since 2022 and may be amended again. Confirm anything that affects a decision with the building official in your jurisdiction.